Does a larger yard meet a 500-request daily target?
Decision: none of these examples meets the whole daily target. A larger storage yard alone does not establish sufficient operating capacity.
The three executed cases share 500 container-handling requests, the same mixed arrival stream, three machines, operating schedule and baseline policy. Geometry and initial stock arrangement differ. The comparison does not isolate yard capacity as a causal variable.
| Example | Demand | Within day | Later | Unfinished at run end | Rehandles |
|---|---|---|---|---|---|
| Small | 500 | 279 | 59 | 162 | 68 |
| Medium | 500 | 287 | 61 | 152 | 0 |
| Large | 500 | 280 | 61 | 159 | 0 |
For each case, within-day completions + later completions + unfinished work = 500. Day-end shortfalls are 221, 213 and 220 respectively. Later completions never count as daily throughput.
What management can conclude
The Medium example completed eight more requests within the day than Small and seven more than Large. These deterministic sample differences are not statistical confidence intervals or a customer-specific recommendation. All three examples leave a material day-end shortfall.
Evidence needed before a real decision
- Dimensioned site and feasible layouts, initial stock, occupancy and dwell times.
- Actual hourly road/rail arrivals, shifts and service commitments.
- Measured machine and handling parameters, dispatch and storage rules.
- Operating and investment costs, disruption scenarios and repeatable validation.
Recommended next action
Scope a comparative operating study using the terminal's own inputs before choosing an investment. Review the original PDF and Excel for each example in the interactive evidence browser.
This is our example terminal. Yours may be different. Let's test your operation.